When in the construction process should lighting design begin?
In new builds, lighting often only becomes a topic when the luminaires are chosen – shortly before moving in. By then, however, the most important decisions have long been made: where supply cables run, where switches sit and whether a concrete ceiling contains a housing for a light line are all determined during shell construction and electrical installation. Lighting design therefore belongs at the start of a project, not at its end.
As a rule of thumb, lighting design begins as soon as the planning-permission drawings are finished. At that point floor plans, room uses and ceiling heights are fixed, and lighting outlets, dimmers, controls and wiring can still be planned in without extra cost.
| Construction phase | What lighting design defines in this phase |
|---|---|
| Planning-permission drawings finished | Lighting concept: which room needs which light (general, accent and ambient lighting), first luminaire types, control concept |
| Before the electrical design | Position of lighting outlets in the CAD reflected ceiling plan, switch and dimmer positions, control cables, locations for power supplies |
| Before the shell (concreting) | Recessed profiles and luminaires in concrete: routing, technical sections, cable routes, coordination with the structural engineer |
| Interior finishing (drywall, plaster) | Recessed profiles in plasterboard and timber, connection to the finished surface, access for maintenance |
| After surface work | Installation of luminaires and light inserts, sampling of the lighting effect, commissioning and fine adjustment |
Which mistakes cannot be corrected later?
Luminaires can be replaced. Anything missing from the shell and the electrical installation, by contrast, can only be added later with considerable effort. Typical examples:
- Missing outlets and supply cables in concrete ceilings. Whatever was not provided for in the ceiling can later only be solved with surface-mounted luminaires or a suspended ceiling.
- Light lines without a prepared housing. Light lines integrated into concrete are created in the formwork. Cutting channels into a reinforced concrete ceiling afterwards interferes with the load-bearing structure and is only possible after a structural assessment.
- No space for the technology. Power supplies and terminals need an accessible location. In the LightLineLed system for concrete, a dedicated driver-profile section is provided for this – at least 50 cm, in practice usually 1 m.
- Too few feed points for long light lines. LED strips have a maximum permissible feed length. Where additional feed points are needed, the cables must be laid in advance.
- No control cables. If you want to dim, store lighting scenes or integrate the lighting into a smart home later, you need suitable cables and control gear depending on the system. During shell construction this is a minor detail; afterwards it often is not.
Some decisions, on the other hand, can be left open for a long time: the colour of light of a light line can still be sampled in the finished room within the suitable combination, and surface-mounted or pendant luminaires can be selected shortly before installation – provided the outlet is in the right place.
What does lighting design cost at MPW?
MPW offers lighting design in four packages. The prices are guide prices according to the overview of services and prices; the exact scope is defined in the quotation.
| Package | Content | Net | incl. 20% VAT |
|---|---|---|---|
| Basic project planning (lighting concept without CAD plans) | Analysis of the room situation, recommendations for luminaire types, placement and control, sketches, energy-efficiency advice | €500.00 | €600.00 |
| Standard project planning (lighting design & project planning – small) | Lighting concept, CAD reflected ceiling plan with lighting outlets, luminaire selection, coordination with the electrical installer, advice on dimming and smart home | €1,000.00 | €1,200.00 |
| Premium project planning (lighting design & project planning – large) | in addition, comprehensive lighting calculations and simulations, planning documentation for architects and electrical installers, concepts against glare and light pollution | €2,000.00 | €2,400.00 |
| All-inclusive package | all services of the premium project planning plus site supervision, coordination with all trades, on-site inspection, commissioning and fine adjustment | €3,500.00 | €4,200.00 |
The first three packages include one draft and two revisions; further revisions are charged separately. MPW charges individual services by time spent, for example lighting consultation at €120, CAD lighting design at €135 and DIALux lighting calculation at €150 net per hour. On-site appointments incur a travel charge of €0.50 net per kilometre.
Part of the planning costs is refunded if you purchase the luminaires through MPW: if you order at least 51% of the quotation, 50% of the project planning fee is credited; if you commission the entire project, 100%. The amount is deducted from the final invoice.
Which package suits which project?
- Basic: for smaller rooms, individual living areas, renovations and simple modernisations where basic lighting advice is sufficient.
- Standard: for flats, detached houses and commercial premises up to approx. 200 m² – in other words, the typical new build.
- Premium: for large residential buildings, restaurants and hotels, office buildings and industrial buildings that require lighting calculations and simulations.
- All-inclusive: for large projects and for anyone who wants the implementation on site to be fully supervised.
You will find all services in detail under lighting design packages at a glance.
How does a lighting design project work?
- Arranging an appointment by telephone, e-mail or online form.
- Lighting design form and free initial consultation: room sizes, design ideas and special requirements are recorded.
- On-site appointment or visit to the showroom, depending on the project.
- Concept development: a combination of general, accent and ambient lighting, energy-efficient solutions and controls.
- Lighting calculation and detailed planning with simulation of different lighting scenarios.
- Presentation and quotation with lighting plans, product proposals, control concept and cost breakdown.
- Implementation and installation coordination, on request with specialist partners from the MPW network.
- Acceptance and fine-tuning after installation.
If a calculated verification is required – for workplaces, for example – MPW prepares a DIALux lighting calculation.
What should you bring to the initial consultation?
The more complete your documents, the more specific the first meeting will be:
- planning-permission drawings or floor plans with ceiling heights, and sections if available
- planned use and furnishing of the rooms, especially kitchen, dining table and workplaces
- material of ceilings and walls (concrete, brick, drywall, timber)
- wishes regarding controls, dimming and smart home
- pictures or examples of the desired lighting atmosphere
MPW's lighting design checklist helps you prepare. The easiest way to arrange the free initial consultation is via the contact form.


