Installing light lines in concrete: what must be decided before pouring?

In short: Before the concrete is poured, the routing of the light line, the later surface (fair-faced concrete, filler or plaster), the position and length of the technical section for the power supplies, the cable routes and the coordination with reinforcement and structural design must all be fixed. The actual lighting technology – visible profile, LED strip and cover – is only fitted after the surface work, so the colour of light and lighting effect can be sampled later in the finished room.

Dining area with long LED light lines integrated flush into the ceiling

How is a light line created in concrete?

A light line integrated into the ceiling looks as if it were part of the concrete – and that is exactly how it is built. In MPW's LightLineLed system, a recessed profile is fixed to the formwork and cast into the concrete. It forms a permanent housing in the component, comparable to a flush-mounted box for a light line. The actual luminaire insert, consisting of visible profile, LED strip and cover, is only added once all construction and surface work has been completed.

This separation has two consequences: everything concerning the housing must be decided before concreting. And everything concerning the light itself can be prepared, tested and fitted later under clean conditions – the sensitive LED technology does not have to go through the construction phase.

Which decisions must be made before concreting?

TopicWhat is definedCoordinate with
Routing and geometryPosition of the light line in relation to room axes, furniture and circulation routes; corners, changes of direction, T-junctions and crossingsBuilding owner, architect, lighting designer
Finished surfaceFair-faced concrete, filled surface or interior plaster – the connection to the profile depends on thisArchitect, master builder
Technical sectionPosition and length of the driver profile for power supplies and terminalsLighting designer, electrical contractor
Cable routes and power feedSupply cables, conduits and additional feed points for long linesElectrical contractor
Reinforcement and concrete coverProfile routing, concrete cover, bends and, where necessary, replacement reinforcementStructural engineer
MaintenancePlanned removal path for the luminaire insert, accessible technologyLighting designer, electrical contractor

How much space do the profile and technology need?

For installation in concrete, LightLineLed documents two profile heights: the mounting profile that holds the luminaire insert is 37 mm high, the driver profile for the supply technology 64 mm. At least 50 cm of driver profile must be provided for technology and terminals, in practice usually 1 m – depending on line length and space requirements. Power supplies in the flush-mounted driver profile may be no more than 18 mm high.

The first reinforcement layer at 35 mm shown in the documentation is expressly only an example. Changes to the reinforcement are permitted only after structural assessment and approval and must not be made arbitrarily on site. According to MPW's recommendation, the conduit is introduced at the start of the driver profile, not through the end caps.

How are the profiles secured on the formwork?

The opening of the profile faces the formwork skin; a suitable timber mounting batten positions and stiffens the profile. Then:

  • Align the mounting batten, connect the profiles and fit the end caps.
  • Check alignment and height and secure the profiles against floating, twisting and shifting.
  • Additionally secure end caps and concrete connectors with fabric tape.
  • Moulded parts are available for corners, T-junctions and crossings (90°, 45°, T, X). If a visible shadow gap is intended, the profiles are nevertheless mitre-cut so that the gap does not widen at the corner.

What is different with fair-faced concrete compared with filler or plaster?

With fair-faced concrete, the precisely prepared opening determines the visible edge. The profile is screwed in place before pouring; when the formwork is struck, the screw should be pulled out in a controlled way together with the formwork and timber batten. The combination of drill hole and screw head is therefore tested on a sample beforehand – there is no standard drill diameter.

If the ceiling is later filled or plastered, suitable connection profiles with a protective strip form the transition between recessed profile and finished surface. This allows the same light line to run through rooms with different ceiling surfaces.

When does the light go into the ceiling?

Only in the finished room. After the surface work, the protection is removed, the profile channel cleaned and the actual installation depth measured. The prepared light insert is then connected, fitted with the appropriate safety devices and clipped in. The mounting clips come in three heights – V1 (10 mm), V2 (20 mm) and V3 (30 mm); four clips per metre are specified, at least two per section.

Because aluminium and the plastic cover expand differently with changes in temperature, the temperature of profile and cover is measured before cutting, and room for movement is planned at joints and end caps. The LED output also depends on the installation situation: for the tested concrete combinations, the MPW thermal data sheet recommends up to 22 W/m at an ambient temperature of 25 °C. Find out more under material, heat and thermal expansion.

How are long light lines supplied with power?

Every LED strip has a maximum permissible feed length. For long light lines, the power supply is therefore divided into sections while the visible line runs continuously. In the flush-mounted profile, a double base forms a concealed cable level behind the visible profile; the mounting clips serve both as fixing points and for cable routing. This allows supply cables to reach further feed points without additional cables becoming visible. The concealed cable routing does not, however, extend the permissible feed length: feed points, cable cross-section and voltage drop are planned according to the specifications of the strip used – and before concreting.

Can the light line be maintained later?

Yes, if the service path has been planned. The suitable luminaire insert can be removed for maintenance or modifications while the housing remains in the concrete. Non-destructive servicing requires accessible control gear, suitable cable reserves and a planned removal path – another reason why the technical section belongs in the planning before concreting.

Sections, installation steps and the corresponding PDF instructions can be found on the application page light lines in cast-in-place and fair-faced concrete. Lighting design by MPW supports you in coordinating routing, technology and construction sequence.

FAQ

Frequently asked questions

Does the colour of light have to be decided during shell construction?

No. Routing, technical space, power supply and heat dissipation must be coordinated early. The final lighting effect can be sampled later in the finished room within the suitable combination.

Can a light line be retrofitted into a finished concrete ceiling?

The system is designed to prepare the housing in the formwork. Cutting channels into reinforced concrete afterwards interferes with the load-bearing structure and is only possible after a structural assessment; alternatively, surface-mounted or pendant solutions can be considered.

May a driver profile be used along the entire length?

A continuous flush-mounted driver profile does not allow the intended fall protection, because its retaining clip only engages in the mounting profile. Technical sections and safety points are therefore planned together.

Who decides on the reinforcement?

The structural engineer. Profile routing, concrete cover, bends and any necessary replacement reinforcement must be structurally coordinated; changes to the reinforcement are only permitted after assessment and approval.

More guides

When should lighting design start in a new build – and what does it cost?

When lighting design should start in a new build, what it costs at MPW (from €500 net) and which mistakes can hardly be corrected once the shell is complete.

LED light lines in drywall and timber: which profile, which cover, how much heat?

LED light lines in plasterboard, OSB, solid timber and CLT: which recessed profile fits, which cover belongs to which profile and how much power is possible.

How much light does each room need? Lux levels for homes and offices

Lux levels according to EN 12464-1 for offices and workplaces plus guide values for living spaces – with tables, lux and lumen explained and an example.

DIALux lighting calculation: when is proof required and what does it contain?

When a DIALux lighting calculation is useful or required as proof, which values it contains, which documents are needed and what it costs at MPW.

Planning LED strips properly: colour temperature, CRI, IP rating, power supply and dimming

How to plan LED strips: suitable colour temperature, CRI, IP rating, power supply, power feed and dimming – with tables and a worked example for 24 and 48 V.

Light Lines in Concrete: What Must Be Fixed Before Pouring